Weekly Project Update

Project Website
Weekly Project Update

Cipole Road Railroad Crossing Replacement

A contractor for Washington County has closed Cipole Road to replace the railroad crossing (just south of Herman Road) Tuesday April 16th through Thursday April 18th.  Cipole Road traffic is being detoured via Herman Rd, 124th Ave, and Tualatin-Sherwood Rd

Tualatin-Sherwood Rd and Nyberg St from Martinazzi to I-5

The permanent lane lines along eastbound Tualatin-Sherwood Road and Nyberg Street were installed at night last week. Final pavement markings (to help drivers more easily see what lane to be in) are being installed tonight (April 18th) and tomorrow night (April 19th), weather permitting.  Expect delays on striping night.

67th, 68th Avenues and Sagert Street

The contractor is scheduled to install the remaining raised curbing to provide a separate walkway/ bikeway on the Sagert Street bridge tomorrow April 19th (weather permitting). 

Tualatin- Sherwood Rd (from Teton Ave to Sherwood)

Washington County’s contractor is adding travel lanes and pathways along Tualatin-Sherwood Rd from Teton Ave west into Sherwood.  They are also building a new 66” water line to carry Willamette River water to Beaverton, Aloha, and Hillsboro. They recently shifted traffic to the south side of the road and are now working on excavation along the north side of Tualatin-Sherwood Road for the widened roadway and pathway.  The contractor plans to close Wildrose Place just north of Tualatin-Sherwood Road (just west of Cipole Rd) April 8-22 to install part of the new 66” water main.

More information is on the Washington County website at Tualatin-Sherwood Road (Langer Farms Parkway to Teton Avenue) | Washington County, OR (washingtoncountyor.gov)  and Road closure / traffic information at Road Closures & Traffic Advisories | WC-ROADS

Boones Ferry Rd from Tualatin-Sherwood Rd to Sagert St and from Ibach St to Iowa Dr

The contractor and utility companies have completed the new sidewalk, ramps, traffic signal, and utility work at the corner of Boones Ferry Road and Warm Springs Street. 

The contractor has poured the foundation and installed conduit for a new traffic signal pole on the southwest corner of Boones Ferry Rd and Avery St to accommodate a short right turn lane for eastbound traffic on Avery St turning right to head south on Boones Ferry Rd. More information is at www.boonesferrycorridor.com.  Construction is anticipated to resume in late April when the concrete has cured and the new pole is delivered.

Sagert Court Paving

Construction is planned in the next couple of weeks to pave Sagert Court, a currently unpaved cul-de-sac south of Sagert Street, west of Boones Ferry Road

Teton Ave Rail Crossing (Between Avery and Tualatin-Sherwood Road)

A contractor for the railroad plans to close Teton Avenue at its railroad crossing (between Avery Street and Tualatin-Sherwood Road) to replace the railroad crossing Friday July 7th to Monday morning July 10th.

Herman Rd (Tualatin Rd to Teton Ave)

The contractor is working along the north side of the road connecting the irrigation system and doing final cleanup.

Plambeck Gardens - Boones Ferry Rd south of Norwood Rd

A developer is constructing the Plambeck Gardens affordable housing complex on the east side of Boones Ferry Road south of Norwood Road and south of Horizon Church. 

108th Avenue (Tualatin Rd to Leveton Dr)

A contractor for Lam Research is building frontage improvements along 108th Avenue in conjunction with development on the Lam Research site.

Martinazzi Ave Sewer (Seminole Trl to north of Sagert St)

On Monday April 22nd, Council will consider awarding a contract to install a new sewer main under Martinazzi Avenue from Seminole Trail to north of Sagert Street and repave this portion of Martinazzi Avenue and Sagert Street in the area of the recent traffic signal project and east to the Sagert St bridge over Interstate 5.

Reservoir and Pump Station at Aquifer Storage and Recovery (ASR) Site

The City has released a Request for Proposals (RFP) for a professional Engineering firm to design a new reservoir and pump station at the aquifer storage and recovery (ASR) site in the Ibach neighborhood.  This will provide additional water storage and service capacity for the southern part of Tualatin.

   

 

Updated: 4/18/2024

 

To download a printable copy of previous project updates see attachments below.